Fort Greely Sewer Outfall Inspection

Coffman performed a condition assessment for 4,150 feet of 14-inch gravity sewer at Fort Greely, Alaska. The project included closed circuit television (CCTV) inspections of the gravity sewer pipe from the main collector to the treatment plant, and then to the treatment plant to the outfall. Coffman identified defects and made recommendations for rehabilitation.

The fast-track inspection was completed in less than two weeks, from contract award to site demobilization. Coffman’s team was available to meet the client’s expedited inspection schedule.

Industries:

  • Energy & Utility

Services:

  • Civil Engineering
  • Trenchless Technology Engineering